How long does a typical implementation project take?

This does vary according to each project requirement. Ideally we plan for a 4 month project time line.

Month 1. - Project establishment, IT infrastructure, data conversion programming

Month 2. - User training, test conversions, system configuration, data conversion test & balancing

Month 3. - 2nd data conversion, some parallel transactions, on-site support, end of month final data conversion.

Month 4. – Live operations, on-site support services.